Monday, 29 March 2010

Timber Frame Assembly-Day 1



2 hours later
Kestrel Construction have
the ground floor walls are up













1st wall panel is errected















Sole plates attached
to concrete base






That's the way to do it!

Lorry unloaded with use
of Telehandler

Saturday, 27 March 2010

The House is on its way!


1st Lorry packed and ready to deliver

Monday, 22 March 2010

22-27 March All Quiet for one weeks' peace










Timber Frame from English Brothers, waiting for delivery-
with hopefully the correct dimensions to fit concrete base!!






Nothing to do except watch the concrete dry and listen to the noisy neighbours- and there are no paw prints from our friendly neighbour either!

Friday, 19 March 2010

19 march 2010 Groundworks Complete

Thanks to Kevin and his dedicated crew
from Greenways Construction, the groundworks were completed on time.

Wednesday, 17 March 2010

17 March 2010 Foundations poured


concrete poured










met the neighbour








Sewers covered

Tuesday, 16 March 2010

2010 march 16- Ready for 2nd pour


Boarded ready for 2nd pour



Underfloor heating pipes



Pressure tested

Monday, 15 March 2010

15 March 2010- Foundation/heating






The secret of the strength
is the 45kg of needle per
cubic metre of cement










Saturday, 13 March 2010

March 2010- Foundations





8/3/2010. All pegged out.
Looks like trying to fit a quart
into a pint pot.






10/3/2010. First dig into soil and
"Insulslab" pods ready for laying .
This system will provide an extremely
strong and well insulated slab





12/3/2010
Pods laid out ready for 1st
pour of SFRC
Steal Fibre Reinforced Concrete

Jan 2010- Time to fence in the Estate!



























Now you see it- now you don't




Friends and family inspect




Friday, 12 March 2010